Travel early warns Great Western Railway, as engineering work will affect Christmas trains
Those hoping for a late Christmas getaway are being warned to travel earlier by Great Western Railway.
Planned engineering work means no trains will run between London Paddington and Reading on Sunday 24 and Wednesday 27 December; and reservations for trains towards Devon and Cornwall on Friday 22 and Saturday 23 December are already almost sold out.
No trains will operate to or from London Paddington station on Sunday 24 and Wednesday 27 December, as Network Rail begins work on the new HS2 station at Old Oak Common. Services are not scheduled to operate on Christmas Day or Boxing Day.
- Most GWR services start or terminate at Reading instead of London Paddington
- Limited GWR and Elizabeth line train services will run between Reading and Ealing Broadway
- Connecting Underground services will run from Ealing Broadway into central London
If you need to travel on 24 or 27 December, please allow plenty of time to reach your destination as journey times will be significantly longer than normal. Service will also finish earlier than usual on Sunday 24 December, and all journeys will need to be completed by approximately 2230.
Customers looking to travel on either of these days should consider travelling on alternative dates for a more comfortable journey.
According to reservations data, trains between 1100 and 1500 on Friday 22 and Saturday 23 towards Devon and Cornwall are almost sold out, and those looking for a more comfortable journey are advised to travel before 0930.
Dean Haynes, GWR’s Station Manager for London Paddington, said:
“As we continue to invest in our railway, we will only be able to run trains to and from Reading and Ealing Broadway on 24 and 27 of December.
“To keep you moving, we have been working with other train companies to provide alternative routes. However, if you can travel on the days before or after, you should consider doing so because journeys will take much longer while the work takes place.”
Joanna Grew, Network Rail’s Industry Programme Director, said:
“Over the Christmas period, from Sunday 24 to Wednesday 27 December, we will be carrying out essential preparatory drainage and railway infrastructure works as part of the construction of HS2’s new station at Old Oak Common near London Paddington.
“As part of this preparation, we also need to close the railway into Paddington on Sunday 26 November where we will also be completing essential railway works between Slough and Paddington which will enable a more reliable railway.
“We appreciate there is never a good time to disrupt journeys but whenever possible we do this at times when fewer people are travelling, such as at Christmas, on bank holidays or at weekends.
“We thank passengers in advance for their patience and urge them to please check before they travel.”
Customers travelling to or from central London can do so using London Underground’s District or Central line services at Ealing Broadway. The Elizabeth line will not operate between Ealing Broadway and London Paddington.
Alternatively, GWR tickets can be used with South Western Railway between Reading and London Waterloo, or on Chiltern Railways between Oxford and London Marylebone.
No Heathrow Express services will run during this time. Customers travelling to Heathrow Airport from central London should use the Piccadilly line instead.
Elsewhere on the GWR network, no train services will be able to stop at Southampton Central on Sunday 24 December, or from Wednesday 27 to Friday 29 December.
Cardiff to Portsmouth Harbour trains will divert via Eastleigh (avoiding Southampton Central) before resuming their normal route from Fareham. Customers for Southampton Central should change at Eastleigh for replacement buses.
For the latest information, visit GWR.com/Christmas.
Contact Information
Notes to editors
First Greater Western Limited, trading as “Great Western Railway” (GWR), operates trains across the Great Western franchise area, which includes South Wales, the West Country, the Cotswolds, across southern England and into London. GWR provides high speed, commuter, regional and branch line train services, and before the covid-19 pandemic helped over 100 million passengers reach their destinations every year. GWR has been awarded a National Rail Contract to continue operating the Great Western network, which shall run up to 21 June 2025, with the potential for a further three years at the Secretary of State’s discretion. Find out more here: https://www.gwr.com/about-us